Mad River Path

Imagine a brilliant October morning in the not-so-distant future. A wide and well-graded path runs the length of the Valley. In some places, it parallels VT-100, and in others, it meanders through adjacent meadows. Along the Path, groups of children are riding scooters to school, a young parent is pushing a stroller, morning commuters are biking to work, an older couple is on their way to the grocery store on e-bikes, and a group of tourists is rolling their bikes to a rack in front of the trail-side farm stand.

This is the Mad River Path of the future, an active transportation corridor extending from Warren to Middlesex!

Wooden bridge or walkway through a forest with green trees and sunlight filtering through the leaves.
Wooden bridge or walkway through a forest with green trees and sunlight filtering through the leaves.

The Mad River Path active transportation corridor will:

  • + Connect Warren to Middlesex with a multi-use path traveling parallel with, but separated from, VT-100 within the state right-of-way. 

  • + Improve pedestrian and bicycling safety

  • + Provide inclusive and accessible alternatives to vehicle travel

  • + Connect to state-wide trail networks, including the Velomont and Cross Vermont Trails.

  • + Enhance the Mad River Valley’s recreation assets

The Mad River Path will improve the well-being of all and infuse the Mad River Valley with new energy for cooperation within and between our communities.

Background

In 2016, the MRV Moves Active Transportation Plan established a comprehensive valley-wide vision for connected trails, roads, and sidewalks in the Mad River Valley (MRV). MRV Moves called for a “consistent, cohesive and connected regional system” that would provide safe access between villages, schools, and businesses. The plan identified specific trail connections and highlighted the Route 100 corridor as a critical spine for the regional network. In 2023, Mad River Path and MRV Planning District successfully secured an $84,000 Transportation Alternatives Program grant to assess the feasibility of this opportunity.

A person with brown curly hair and a brown jacket points to a poster with green dot stickers on it, displaying survey results and information about a public process.

Practical Approach

Using (and improving) existing trails, focusing on village-to-village connections, while reusing existing sidewalks through the village centers, interim configurations at bridge crossings, employing boardwalks through ecologically sensitive areas, and improving flood resilience, are examples of a practical “can-do” approach to design and construction of the path.

Two young people are walking along a forest trail, carrying tools for outdoor work. There is a wheelbarrow in the foreground, and a signboard on a stand near the trail. The forest is dense with green leaves and tall trees.

Long-Term Commitment

Completing the Mad River Path is a long-term commitment that requires a sustained effort by the entire valley. Together, we will manifest a beautiful Path that connects communities, provides access to nature for everyone, improves well-being, reduces carbon emissions, and becomes a driver for the sustainable recreational economy.

Coalition of Support

The work begins by building a broad coalition of support. Our partners include the local town governments, selectboards, conservation commissions, and planning commissions. We work alongside landowners, nonprofits, and local businesses. We are building support with our state representatives, as well as other statewide networks like VMBA, the Cross Vermont Trail, and Velomont. We develop relationships with grant funders like VTrans and business sponsors.

Project Timeline

Scoping Study (2024-2025)

In December 2023, we worked with our partners to apply for funding to undertake a scoping study, administered by the VTrans Transportation Alternatives Program.  In April 2024 we received an $84K grant for an engineering study of the proposed path. The study broke the project into sections, identifying priorities, opportunities, and challenges. It solicited and took into consideration public input. The scoping study was finished in 2025 and its findings presented at a final public meeting.

Implementation (2026-)

Following the successful scoping study, our municipal partners will become eligible to apply for final design and construction funding through VTrans’ Bicycle & Pedestrian Program and Transportation Alternatives Program. The funding will come from the federal transportation budget and will require a 20% local match. Implementation will be taken in sections, with each section having its own “independent utility” (making it useful even if the rest of the path is not yet completed). While it will take years to complete the entire path, the Kingsbury Greenway became the first section to be completed and upgraded to an adaptive standard in Summer 2026.


2023


  • Fall 2023: Warren, Waitsfield and Moretown approved local funding for the scoping study.

  • December 2023: Submitted application to the VTrans Transportation Alternatives (TAP) Program for funding to assess the feasibility of a multi-use path along the VT Route 100 right-of-way from downtown Warren to the intersection of VT-100 B and Hooper Ln. in Moretown.


2024

  • April 2024: The Central Vermont Regional Planning Commission (CVRPC), Mad River Path, and MRVPD receive an $84K Scoping Study Grant.

  • June 2024: The committee chooses VHB as our scoping study partner.

  • August 2024: The Corridor Advisory Committee is created with the representation from four valley towns.

  • September 2024: The first Advisory Committee Meeting, and project kickoff

  • November 2024: First active transportation corridor public meeting

  • March 2025: Second active transportation corridor public meeting


2025

  • October 2025: Final meeting to present findings of the scoping study

2026


  • August 2026: Kingsbury Greenway becomes the first segment to be upgraded to a fully adaptive standard

Implementation

Wooden pathway winding through a dense, green forest with tall trees and lush foliage.

The 2027 Implementation Plan is under development and will be posted in November 2026.